Thursday, December 1, 2016

Construction - Second Story South Wall

The previous post concerned the construction of a permanent and temporary second story floor on which to work on the second story walls and roof.  Here we are dealing with the 10+ foot south window wall for the second story, the top of which is a little over 20 feet above the first story floor.

Change in Window Configuration
Click on the drawing

Originally I planned to use seven double-window sets as clerestories in the south wall, as shown in the drawing. When I laid out side-by-side the seven pre-made window sections containing two windows each, they clearly were too crowded. Consequently, I reduced the number to five double-sections, stood them up and viewed them from the street. The proportions were definitely better.  Then it made sense to add back a couple of single windows as a way of softening the monotony of the facade and to stay in compliance with the minimum code requirement of 4% glass-to-floor area.  So I dismantled the two extra sections and reused the components to make wall sections for single windows that will have the same 3' x 5' dimensions as the individual windows in the double sets.

Adding Height to the South Wall
An end of the truss jig was cordoned off with
 2 x 4s for making 24" x 15" inserts; the plywood,
  nailed to a 2 x 4 frame, serves as a gusset 
The plans call for 12" thick cathedral ceiling for the first story shed roof that extends southward from the second floor wall.  Accordingly, the height of the wall was designed to be high enough to accomodate windows above the roof that will be pitched at 12/2.5. However, I will be using ceilings that are +/-20" thick. If the wall height isn't increased by at least 8", the pitch of the roof would have to be lowered to keep the roof from overlapping the bottom of the windows.  This is not an option because a slope of less than 12/2.5 is not recommended for metal roofing. The pre-made window sections that will comprise most of the wall were designed for an 8' wall and will therefore have to be heightened by a total of 24"  -- 16" to satisfy the original drawing plus another 8" to accomodate the thicker roof. Unfortunately, the additional 8" will place the sills above the 44" maximum height for egress windows but, fortunately, only the single window in the bedroom at the east end of the house will be affected.  For it to meet code, there will have to be a permanent riser below it on which an occupant could stand while exiting in an emergency.

I temporarily modified the jig that I used for wall trusses to make 24" high inserts to go between the window sections and the floor.  Admittedly, the inserts looked a little goofy but, when tied in with bolts, nails and strapping, they did the job.  

Raising the Wall
The four wall sections before raising; the section with the saw
laying on it and without its top and bottom plates is to be
raised last (click on the photos to enlarge them for more detail)
The window sections comprised most of the second story south wall but a couple of wall trusses were needed at both ends of the wall to connect later with the east and west rake walls. As soon as the extra trusses were ready, I cut the four 2 x 6 top and bottom plates to length, laid them side-by-side and marked them for attaching to the wall sections and the new trusses.  Then it was a matter of nailing them to the trusses and wall sections while keeping the outer edges of the tandem 2 x 6s exactly 15" apart, the same as the wall components.  I divided the 58' wall into four units in order to keep the weight within reason for raising.  I left the top and bottom plates off of the shortest unit since it would be the last to be raised and might need narrowing in order to fit into the space between the adjacent units that were already up.
Unsuccessful attempt at using wall jacks

Step-son, Keith, helped raise the walls. We assumed that the sections would be too heavy for raising without wall jacks but, after we were half through with using them for the first unit, we realized that they were not properly adjusted for a 10' wall and had to lower the wall back to the floor.  Instead of adjusting the jacks, we removed them, under the assumption that we had under-estimated our ability to raise the wall without them. So, in order to keep the wall from sliding over the edge of the floor, we used rope to tie the bottom and the top of the wall to the existing wall to the north.  Then two of us raised the first unit surprisingly effortlessly and continued to do so for the other three units.

As soon as the first three units were upright and the bottom plates were temporarily fastened to the floor with duplex nails and the top plates fastened together with clamps, we could dry-fit the unattached 2 x 6 plates for the last unit then attach them to the unit.  When we raised the unit, it fit nicely between the two adjacent units.

Aligning and Securing the Wall
As the units were raised they were stabilized with braces between the wall and the floor.
Second story wall housing a total of twelve 3' x 5' windows
Fortunately, the raised wall was perfectly plumb in an east-west direction, which was to be expected because the individual window units were shop-made in a jig. And each of the four wall units was checked for square while still laying on the floor before nailing on the top and bottom plates. All that remained was to get the wall (a) straight at both the top and bottom, (b) level on top and (c) plumb in a north-south direction. The braces were attached to the wall with drywall screws so the screws could be backed out and refastened as the wall was tweaked.  The duplex (double-headed) nails between the bottom plates and the floor provided the same flexibility.
The wall from a different perspective; notice the nailers over
the window openings for safety reasons; the height is just
over ten feet; the window sills are slightly too high to meet
 code for egress

We started the alignment by straightening the bottom and the top using taut mason's lines while loosening and refastening the tops of the braces and the duplex nails as needed. The clamps sufficed for the top temporarily.  As with conventional 2 x 4 or 2 x 6 walls, we used a double top plate, i.e., a second layer of 2 x 6's stacked on top of the ones that were nailed to the wall sections before raising the wall.  We installed the ones on the interior side of the wall first and used them to pull the wall perfectly straight and hold it straight, assisted by a mason's line.  Of course, as is standard practice, we staggered the locations of the ends of the boards relative to the first tier of top plates so as to stiffen the wall.

The floor under the wall was not perfectly level so the top of the wall also was not perfectly level, primarily in one area.  In order to correct the problem, we used shims under the bottom plates to level to a mason's line the top of the wall.

All that remained now for proper alignment was to plumb the wall in a north-south direction and secure it definitively to the floor.  For plumbing, we used shims under the bottom plates as necessary while loosening and reattaching the braces.  Then we used 6" construction screws and nails to fasten the bottom of the wall to the floor joists and band-joists.  

Our location places us at risk for two catastrophes.  Two hundred feet below us is an abandoned coal mine and subsidence is not uncommon in ours and the surrounding counties.  Also the New Madrid fault in southeast Missouri near its border with Tennessee has a 25 - 40% chance of a magnitude 6 earthquake within 50 years and a 7 - 10% chance of a 7.7 magnitude.  Either would cause serious damage in the St Louis region. Consequently, the final job to secure the wall was heavy hurricane strapping to tie it to the lower floor framing and to the major beam under the catwalk.

Installing Cripples
The purpose of cripple studs under the window openings is mostly for fastening sheathing
Cripples anchored at the bottom by 2 x 4s
and drywall but a secondary function is to support the sills under the windows which, in turn, supports the window. The latter function is more important for conventional 2 x 4 or 2 x 6 walls whereby windows are supported usually by one 2 x 4 or 2 x 6 installed flatways.  With our truss walls, each window is supported by two 2 x 6 sills installed on edge thereby making the secondary role of the cripples largely moot.  


I spent a few minutes making a temporary jig in which to nail the double cripples to a short 2 x 4s before nailing them in place.  I opted for the 2 x 4s cross-ways of the bottom plates rather than toenailing the cripples directly to the plates to make the cripples easier
Quickey jig for nailing cripples to 2 x 4s
to install and for more secure fastening at the bottoms. The tops were notched around the sills so they were well-nailed on top.  I might have opted for toenailing if the bottom of the wall was to be exposed to the exterior in order to avoid
 thermal bridging by the 2 x 4s. But not to worry, the bottom of the wall will serve as the top part of the wall for the first story and the bottom third of the cripples will receive drywall instead of sheathing.

All exterior walls for the house are designed for trusses 24"oc due to their stiffness. The cripples, however, are 16"oc just like the typical 2 x 4 wall framing of most houses.

Monday, November 21, 2016

Construction - Second Story Floors (Permanent and Temporary)

Subfloor in place; the catwalk will join the bedroom in the
distance with the balcony office in the forefront; the open
space overlies the living room and reveals the vaulted
second story ceiling
As explained in a recent post, I elected to build the interior bearing walls ahead of the exterior walls which is probably something a contractor would never do. And the stick-built first story exterior walls will remain in abeyance until the second story is built clear to the roof.  The reason for this sequence is that the first story floor is weather resistant concrete while the subflooring for the second story is OSB that needs to be covered as soon as practical.  And the second story exterior walls support the roof so the floors have to be in place before the the walls and roof can be built. 


A temporary floor (light color) fills in the open spacethe dark wood in the next photo is salvaged lumber supporting a temporary floor
I use the plural form, "floors", because only about two-thirds of the second story floor is permanent, as described in a prior post. The other third is temporary in order to serve as a scafflod on which to build the south and west exterior second story walls before raising them.  One of the temporary floors was built soon after the permanent subfloor went in (above photo)  but the other had to wait until more beams had been erected.

More Beams and Another Temporary Floor
As the drawing shows, the second story west wall will be suspended over the master bedroom on beams. Their construction using LVLs was not unlike that described in a prior post. Once the beams were in place, I could then fill in with a temporary floor the space between the new beams and the permanent floor such that the entire second story now had a floor of some kind on which to work safely while building the
exterior walls and the second story roof.
Click on the drawing to enlarge for better viewing

Fortunately, I have enough lumber salvaged from several tear-downs to frame out the temporary floors.  I screwed down 1/2' plywood sheathing as the floor surface then painted it with exterior stain in order to protect it as much as possible since the plywood is not intended for exterior use.  I am hoping to be able to recycle it or sell it on Craigslist when the temporary floors are removed.

The plans specified a beam comprising two LVLs fastened together but, since the exterior wall resting on it will be 15" thick to match the other truss walls, I installed a third LVL such that the outer edges of the two beams were 15" apart.  Then I covered the beams with subflooring to add rigidity.
The three-LVL beam stained for temporary
protection from the elements

Stops for Wall Raising
In order to add a measure of safety for an eighty-something, agility-challenged DIYer, I added a couple of safety ropes around the periphery of the second story. However, the main purpose of the 2x4s supporting them is to act as stops to keep the second story south wall from slipping off the edge when it is raised. Consequently, I used construction screws to fasten the supports more securely than could be done with nails or drywall screws.  And I inclined them slightly outward at the top to be sure they would be out of the way of setting the wall later.
Temporary floor between beam and permanent floor stained
for protection until under cover








As described in the next post, the wall was controlled with ropes during raising and the stops were superfluous. But the ropes proved invaluable as I assembled the wall on the floor only a few feet from the edge. The ropes would have stopped, or at least, slowed any falls but I am inclined to think that their presence was more psychological than physical.  After they were in place, I could relax and work near the edge instead of being preoccupied and overly cautious about falling.
A view of the ropes and of the larger temporary floor after staining
The stage is now set for unwrapping the pre-made wall sections, stored in the background under plastic, and laying them out on the floor for assembly; the "boxes" strewn about on the deck, will be used to heighten the wall -- all to be described in detail in the next post.

Saturday, November 5, 2016

Design - Thermal Bridging and Air Infiltration (Cont'd)



This is the second of two posts on thermal bridging and air infiltration. The first post defined the three ways heat gets transferred -- by conduction, by convection and by radiation -- and what is meant by the building envelope.  Then the post focused on the transfer of heat by conduction through the building envelope. This post covers the other two heat transfer modes -- convection and radiation.

Convective Heat Loss
Air infiltration and exfiltration refer to the heat transferred in and out through the building envelope by air in motion -- convection.  Air infiltration is at it worst when winter winds push air through holes in the envelope, especially on windy days when there is a air pressure differential between the side of the building against which the wind is blowing and the leeward side of the building.  Heat is lost even in the absence of wind, however, as interior air exfiltrates, not only because heat seeks cold, but due to a pressure differential.  In summer, air infiltrates for the same reasons.  So here is my understanding of the best practices for controlling convective heat loss via what has come to be known as air sealing:

  • In the first place, design intentionally and build with precision in order to minimize potential holes in the envelope
  • Then seal all unavoidable holes with gaskets, caulk, tape, spray foam and drywall mud
    • Between parallel and touching structural members, such as double top plates
    • Between mud sills and concrete foundations
    • Between structural members and the sheathing
    • Between windows and doors and their rough openings
    • Between drywall intersections, especially walls meeting ceilings
    • Around penetrations in the envelope for such things as vents, furnace pipes, wiring, coaxial cables, electrical boxes and can lights
    • Within window frames; choose those that close against a sealing gasket instead of sliding -- such as casement, awning or hopper instead of horizontal sliders or single or double hung
    • Within double-glazed window panes by the addition of argon gas which, by being heavier than air, impedes heat-conveying convective currents between the layers of glass
    • Through fireplace doors and dampers
  • Use an airlock between outdoors and living spaces
  • Orient exterior doors away from the prevailing winter winds (in our locale, that would be south and east sides of the building)
  • Use air (and moisture) barriers such as latex-painted drywall interiorly and house wrap exteriorly*
  • Then, use a blower door test to measure the integrity of air sealing and identify leaks to be corrected before insulating and drywalling
Convection and Our Project
Super-insulating the walls and ceilings and going all out to eliminate thermal bridging
would not produce a zero energy, or energy neutral, home unless air infiltration is eliminated as well.  Johnston and Gibson in their book say, "A typical house has 2,000 liner ft. of cracks and gaps that allow air in and out, which can represent up to 50% of the heat loss in a building".

One of the advantages of being a task oriented DIYer instead of time oriented contractor, is that there is no reason not to be precise with construction first then compulsive about hole plugging.  I intend to buy a pneumatic caulk gun because I know how tedious, tiresome and time-consuming the caulking will be.

For at least the first story and as much of the second story as my stash of 3/4" salvaged lumber will allow, I intend to use the 3/4" individual boards for sheathing.  I will install them at a 45 degree angle as was commonly done before sheet goods were available.  The 45 degree orientation has two benefits.  When the cladding is attached over it, a row of fasteners will be spread over multiple boards so as not to cause splitting of a given board. And the diagionalization provides shear strength to the wall. The disadvantage of using 1x lumber is that it is impossible to seal all of the spaces between so many boards.  Consequently, I will use recycled 4 x 8 sheets of Masonite on the wall trusses before nailing on the sheathing boards.  I can then caulk from the inside just as if the wall was sheathed with OSB board. The Masonite will also add a quarter inch of thickness for fastening of the metal cladding. Unlike most of the contemporary man-made sheet goods, Masonite is manufactured with natural binders so that there is no worry about VOCs.

As far as air coming in through exterior doors, we will have a large 8' x 14' airlock so that the semi-conditioned air in the lock will attenuate incoming outside air before an interior door is opened.  The door between the kitchen and the screened patio will not be protected by an airlock so it will see little use during the winter.

And needless to say, the earth sheltered parts of the envelope totally eliminate any chance of convective heat loss -- air doesn't pass through dirt and concrete very well!

We are seeking green building certification by either HERS or NABH Green Building Standards (Timeline - Alternative Certifications to LEED).  Part of the certification process is blower door testing to measure air infiltration.  I think we will be ready.


Radiation
Aside from stoves and fireplaces in the living space, the principal source of radiant heat is the sun.  The game here is to admit solar gain when you want it and and exclude it when you don't through the following measures for the northern hemisphere:
  • Orient the building for major solar gain through south-facing windows in winter but block the gain during summer with overhangs, deciduous trees and trellises
  • Incorporate well insulated thermal mass into the structure so as to trap and hold any intentional gain
  • Minimize the amount of glazing on the north and west and, to a lesser extent, the east
  • Use low-E glazing so as to slow the loss of solar heat back through the glass
  • Distribute (diffuse) incoming solar radiation with by either using translucent glass, rather than transparent, or light colors where the sun shines (ceilings, floors and walls) unless there is enough thermal mass to absorb the energy without overheating
Radiation and Our Project
We are intentionally avoiding stoves and fireplaces for the sake of better indoor air quality and to eliminate air infiltration/exfiltration via envelope-piercing chimneys.  Our heating (and air conditioning) system will be passive solar by virtue of the AGS system. But, rather than depend on solar gain in the winter, the gain will come from the summer sun.  (For basic information on the AGS system, click on "Timeline - Annualized GeoSolar" under "Featured Post in the column to the left and follow the trail of posts.  Or go to Wikipedia for a more succinct explanation.)  

Our design calls for south-facing glass with overhangs except possibly one east-facing window in the laundry room.  The overhangs will restrict direct solar gain to the cool/cold months (but with too much in the early fall, which will be grist for a future post on the design of the overhangs). We intend to use translucent glass in most of the second story clerestory windows backed up with light colored ceilings and walls so as to diffuse incoming sunlight instead of creating hot spots on the walls and furnishings. Because of
the AGS system, the concrete floor will remain essentially the same temperature year-round and will absorb the diffused energy gradually. Sunshine falling directly on it will be absorbed without hot spots by coloring it with medium, rather than dark, tones.  (My information on color selection and translucent glass comes from "The Passive Solar Energy Book:  A Complete Guide to Passive Solar Home, Greenhouse and Building Design" by Edward Mazria -- a good read for anyone contemplating passive solar construction.)
_________________________
*As I will discuss in detail in upcoming posts on air barriers and vapor barriers, air control and moisture control are closely related to the extent that to control moisture is to control air as well.

Wednesday, October 26, 2016

Design - Thermal Bridging and Air Infiltration

This the first of two posts on the subjects of thermal bridging and air infiltration

Our building project is defined more than anything by the use of the heat from the summer sun to eliminate conventional heating and air conditioning by a system called Annualized GeoSolar (AGS) but it is also unique in another extremely important way  -- having an envelope that is not just well-insulated but super-insulated.  "Super-insulated" has become the term for envelopes that exceed industry norms and building code R-factors with respect to the thickness of the insulation and control of thermal bridging and air infiltration.

If you are new to the blog or do not know about AGS, a quick study can be had by clicking on "Timeline - Annualized GeoSolar"  under "Featured Post" in the column to the left. Also Wikipedia's description of AGS is also a good overview.

The Envelope
The skin of a building in contact with the outside environment comprises the walls, roof or ceiling, floor, windows and doors collectively known as the "envelope".  A good part of green building boils down to keeping heat from entering (summer) or exiting (winter) the envelope.

Heat Transfer
Heat is transferred in three ways: 
  • Conduction - through solid objects, called "thermal bridging" when it is
    applied to the envelope of buildings; examples are heat passing through a window, both through the glass and through the frame, heat passing through 2 x 4 wall studs and heat passing through uninsulated foundations 
  • Convection - through fluid motion (air is a fluid); when air passes inward through the envelope, it is called "air infiltration"; when air passes outward, it is called "air exfiltration"; examples are air leaks around ill-fitting exterior doors, air leaks around receptacles and switches in exterior walls and air leaks between structural members such as top plates
  • Radiation - in a straight line through space, such as sunlight warming a floor or heat from hot water radiators, infrared space heaters and fireplaces
Best Practices
Following is a review of my understanding of best practices for controlling heat transfer back and forth through the envelope of a house.  The bulleted items that apply to our situation are linked to other posts on the same topic.

Thermal Bridging
The ways to control thermal bridging are..........
Thermal Bridging and Our Project
Instead of using through-and-through framing, we are using wall trusses that virtually
Wall truss
eliminate heat transfer through the wood members.  The walls will be insulated 
to R- 48 with rice hulls 15" thick. Our cathedral ceilings will be insulated to 16", again with hulls, with slightly more thermal bridging through the structural members than the walls, but not appreciably more because we will be using either I-joists or trusses rather than solid 2 x 12s.   We plan to splurge on high-end windows and doors in order to minimize conductive heat loss through these virtual "holes" in the envelope. There will be no windows on the north or the west to suffer wind washing and the windows on the south will be set into the wall 10" to further reduce wind washing.  Insulating the slab floor of our house will be a non-issue since it will be warmed by the AGS system. The slab floors of the garage and screened porch are already insulated as part of the insulation/watershed umbrella.

Cathedral Ceilings
Cathedral ceilings are a conundrum.  They enhance the aesthetics of interior space but can be a challenge to insulate compared to an attic into which any amount of insulation can be piled.  For our cathedral ceilings the jury is still out at the time of this writing as to whether we use man-made I-joists or custom trusses, either of which are a better choice than 2 x 12s for three reasons: (a) the maximum depth of ceiling insulation is determined by the height of the rafters and the height of 2 x 12s is limited to 11 1/4" whereas the height of I-joists can go at least to 16" and trusses can be any height; (b) as we pointed out above, through-and through dimension lumber transmits heat while I-joists and trusses minimize through-and-throughness; (c)  I-joists and trusses are a greener alternative since both are made from sustainable forest products whereas 2 x 12s are almost certain to come from old growth timber, especially in 20+ foot lengths that our project requires.

North Wall and Floor
Since the AGS system requires free exchange of heat between the inside air and the soil behind the wall (and below the floor), thermal bridging (conductive heat transfer) through the concrete is a good thing except for the top few feet of the wall protruding above the insulation/watershed umbrella,   The concrete above the umbrella will be super-insulated to nearly, or the same, R-factor as the stick-built truss walls using EPS solid foam panels on both sides of the concrete portion of the wall (DIY concrete wall insulation).  The top 3' of the wall above the concrete will be stick-built to match the other exterior walls and insulated with at least 15" of rice hulls. 

At the time of this writing, I am thinking about using rice hulls to insulate the inside of the concrete wall above the umbrella by increasing the thickness of the 3' stick-built portion on top of the concrete to, say, 21".  At this thickness, 2 x 6 framing could be butted up against the stick-built wall from below to hold rice hulls against the concrete.  With 3 1/2" of foam board exteriorly and 5 1/2" of rice hulls interiorly, the R-factor of the concrete wall would then match that of the truss walls for the rest of the house.  The extra bulk interiorly would not be intrusive because it would be overhead.

The slab floor is an automatic.  The AGS system will keep it at 74 degrees (+/-4 degrees) year-round.  In winter, it is thermal bridging through the slab that will heat the house; in summer, it is thermal bridging through the floor that will siphon off excess heat. But in order to do so, the soil under it must be bone dry.  Otherwise, water would carry heat away to the water table faster than the solar collector could generate it. Accordingly, the French drains located 10' below floor level and the insulation/watershed umbrella extending 20' outward from all sides of the house should take care of any surface or subterranean water threatening the AGS system.

Conductive Heat Loss (Thermal Bridging) To and From the Thermal Mass
The AGS system is predicated on a large thermal mass comprising the slab floor and the
Umbrella installation in front of the house; the foam board
layer was the third layer among a total of ten layers that
comprise the umbrella
gravel and soil under it as well as the tall earth contact north wall and the soil behind it.  The imperative is to control heat loss from the mass during the cold months so that the heat gained by the solar collector during the warm months is enough for a comfortable year-round floating temperature
 in the living space.  In order to increase the amount of thermal mass and push heat loss at its periphery as far out as possible, waterproofing and insulation extend outward from the house 16 - 20' in all directions, as discussed in design of the umbrella and as demonstrated in three subsequent posts starting with the installation phase.

This post has detailed conductive heat loss through the envelope by thermal bridging. The next post will cover convection and radiation.

Saturday, October 15, 2016

Construction - Back to Dirt Work - Insulation/Watershed Umbrella (Cont'd some more)

This is the third post on the insulation/watershed umbrella.  The first post covered some tasks that had to be done before starting the umbrella then it described the installation of the first three layers of the umbrella.  The second post detailed the installation of the next six layers.  This post covers the last layer -- the topsoil backfill.  

Reminder:  click on any photo to enlarge it to full screen.

Vacillation on Methods
For months, I have dreaded the time when the umbrella had to be backfilled because I assumed that it would have to be done with wheelbarrows and shovels instead of the trackloader in order to avoid damaging the underlying sheet plastic and foam board insulation. The excavation contractor who had done work for us earlier described a method for using the loader safely.  Not only was it rather complicated but I felt that my track loader skills were not up to the task.  Ultimately I did use the loader somewhat like he recommended but only after some trial and error.

By the time we had installed the two layers of carpet and the four layers of sand over the foam insulation, I became convinced that the umbrella might be resilient enough to withstand the weight of the loader.  But I still bought three sheets of 3/4" plywood to lay down in front of the loader on which to drive thinking that the weight would be more evenly distributed and less likely to damage the umbrella.  But this method took three of us -- I drove the loader while two guys moved the plywood.  

Trackloader Saves the Day
First few tentative trips onto the umbrella with the
trackloader before deciding that it could be used for
backfilling without damaging the umbrella
After the first trip onto the umbrella using the plywood, we realized that the soft loamy topsoil, close to 2' deep, would suffice as a cushion as long as I avoided two maneuvers that the contractor warned about -- spin turns or raising the bucket too high.   So I began bringing in the topsoil in straight line pathways and, in so doing, not only distributed the soil but also began slowly to compact the soil over which I passed. Eventually, the compaction was enough that I felt comfortable making looping turns to fill in the gaps in the corners that were left by the straight line pathways.  And, as much as possible, I used straight pathways when smoothing and leveling the grade.

I would estimate the amount of backfill we used over the umbrella at 3 - 4 tandem truck loads or 40 or 50 loader bucket loads.  To
The backfilling about half done; notice that it is easily deep
enough to support vegetation; we plan to use shallow-
rooted native plants eventually even though turf grass
 is going in first to stabilize the soil against erosion in 
the short term
have moved this much fill with wheelbarrows would have been unbelievably arduous and time-consuming.


Perfecting the Grade for Seeding
Final grading with hand tools; ready for seeding
I thought I had done a pretty good job with the loader with regard to sloping the grade over the umbrella for proper drainage and leaving a smooth surface almost ready to seed.  But, on close inspection, it left a lot to be desired.  So I rented a self-propelled tiller and asked friend Pat to help run it for the several hours it took to loosen the soil enough to be able to shape and smooth it with hand tools, which, in itself, took 1 1/2 man-days between my wife's Uncle Archie and I.

Seeding and Stabilizing
Coffee bag burlap over grass seed to prevent erosion
Our long-term goal is to landscape with native plants instead of turf grass but the immediate goal was to establish a cover crop that would prevent erosion of the soil during the heavy rains next spring. Consequently, we planted conventional grass seed with the intention of replacing it over time with ground-hugging shallow-rooted natives (if there is such a thing as shallow-rooted native plants).
Wheat straw over grass seed to prevent erosion

Our soil is wind-blown loess left by the glaciers.  In order for it to have been transported by the wind, the particle size had to have been minute -- a fine-grained silt -- which is highly erodible.  In order to hold it in place on the steep slopes, I cut open recycled coarse burlap coffee bean sacks and fastened them together with hog rings.  After the seed was broadcast, we positioned the burlap over the slopes.  The burlap was stable in the wind so we only needed to anchor it by stapling it to boards laid under the critical edges of it, as opposed to anchoring it also in the middle with landscaping fabric staples.   All but a small section of the remainder of the seeded area was covered with wheat straw for erosion control.
The French drain can be seen in the
shadows to the left
Finally, we used a sprinkler to compact the burlap and straw, to stick the seed to the soil and to jump-start germination.  And luckily, it rain a few days later. 

Tweaking the Solar Collector Before Surrounding It With Topsoil 
Before adding the topsoil to the slope immediately south of the solar collector, I needed to dump six loader buckets of sand into the collector for use later when it goes into service as part of the AGS system. However, as described in a previous post, water collected in the collector numerous times and deposited about a foot of soil that had to be removed. The main reason for its removal was to uncover a French drain that passed under the collector (one of seven placed early onso that it would be available to drain any water falling into the collector after it is finished.  As step-son, Keith, and I pitched the excess soil over the wall of the collector, we shaped the dirt floor so it will direct water to the French drain after it soaks through a thick layer of sand.  The sand overlaying the soil will support the corrugated steel that will adsorb the sun's rays for the AGS system -- the topic of a future post.
Collector after the sand has been added and
spread enough to cover all of the soil

As for the time being, we merely made sure that all of the dirt floor was covered with sand until the collector can be finished then left the rest of the sand piled up.

Insulating the Porch Footing
Another task to be done before finishing the topsoiling was to insulate the screened porch footing.  Since the foundation of the porch is a frost-protected shallow foundation, the footing needed to be insulated on its exterior where not already insulated by the umbrella, i.e., on the three sides not facing west towards the umbrella.  

Future Plans for the Insulation/Watershed Umbrella
Now the only area within 20' of the front of the house not covered by the umbrella is the section in front of the main entrance and the garage.  The umbrella here will be installed next year in conjunction with pouring the sidewalk and driveway.  The umbrella next to the retaining wall west of the house and the umbrella behind the concrete north wall of the house will also be installed next year.
Insulation at the level of the porch footing before backfilling

Landscaping Beyond the Umbrella
The catch basin lies in the rough ground south of the umbrella and the solar collector.  Because the basin is critical for keeping runoff onsite, it and the area around it will be the last portion of the building site to be landscaped.  The basin will give way to a series of rain gardens planted with natives so that rainwater will leave the property underground and purified instead from the surface and contaminated.
Rough area containing the catch basin (click on photo to enlarge it)

I guess we were pretty fortunate considering that it took almost three weeks to install the umbrella without having to deal with any serious rain. The final photo shows the site in mid-October as we return our attention to the carpentry phase in hopes of getting the house under cover before the rainy season in spring and early summer.
Status of the building site after the latest round of dirt work









Thursday, October 6, 2016

Construction - Back to Dirt Work - Insulation/Watershed Umbrella (Cont'd)

The last post covered the first three layers of the insulation/watershed umbrella.  This post deals with the next six layers.  A subsequent post will talk about the last layer -- the topsoil.  
And the usual reminder:  click on any photo to enlarge it.

SAND
Now that the insulation and a thick layer of sand made for a rather squishy surface on which to work, wheel barrows were out of the
A thin layer of sand covers the foam board
question for subsequent layers of sand, so the real work began.  I brought loader buckets of sand to the periphery of the umbrella in three places then we broadcast the sand shovel-by-shovel and broomed the sand until the first layer of plastic was uniformly covered but only half as thick as the first layer of sand. The purpose of using another layer of sand is primarily to serve as a drainage plain in case any water penetrates the top layer of plastic. It also smooths out the transitions as the thicknesses of foam go from 4" to 3" to 2".  The drainage would have been even better by having a thin layer of sand between the first layer of plastic and the foam board as well as on top of the board but I was afraid that the sand would cause the foam board to scoot around when we walked on it and pitching sand was already getting to be a little tiresome.

Intermediate layer of plastic sheeting batten down for the night

PLASTIC SHEETING
We merely butted this second layer of sheeting against the foundation wall instead of mating it with the sheeting extending from under the cement board/stucco covering on the foundation and the retaining wall.  The purpose of this layer is to provide another barrier to water penetrating the umbrella should the top layer of plastic be breached.

SAND
Another thin layer shovel-broadcast and evenly spread.  The purpose of this layer of sand is to provide a drainage plain for any water penetrating the top layer of plastic sheeting. Without it, the weight of the topsoil layer would pinch the two sheets together so tightly that water would trapped between the sheets and not be able to escape down-slope.

PLASTIC SHEETING
This layer was butted against the foundation walls and the retaining wall then the second sheet hanging out from under the cement board/stucco foundation and the retaining wall was shingled over it.  As with the first two layers of plastic, one long piece went from the screened porch to the western end of the excavation, a distance of almost 60'.  A shorter piece was installed between the west wall of the house, the extent of the excavation and in front of the retaining wall, such that it overlapped the first piece in shingle fashion by a large margin.  The two together pretty much used up a 100' roll of plastic.

SAND
The top layer of plastic will be the primary barrier against moisture penetration into the envelope but it is imperative that any moisture it collects finds an unobstructed passage off of the umbrella.  So the last layer of sand provides the drainage plain through which water will easily exit the envelope.  I reasoned that this layer should be little thicker for drainage purposes and to withstand some redistribution as the carpet was tweaked into position.

SALVAGED CARPET
The primary function of the carpet is to protect the sheet plastic from physical damage caused by someone digging in the topsoil layer who doesn't know, or forgets, about the underlying umbrella.  It will discourage aggressive plant roots (although we plan to landscape with native ground-hugging plants with shallower roots).  And burying the carpet is also a green thing in that it keeps it out of the landfill.

I have been collecting used carpet for several years in anticipation of making it the last
The last layer of plastic has been covered with a substantial layer of
sand;  Pat and Roger are in the process of laying down the first layer
of carpet by simply laying it in place and unrolling it, thereby keeping the
appearance side up
layer of the envelope before backfilling with topsoil. Most of my stash of carpet came from friends and family who knew to keep the pieces as large as possible.  As it turned out, I was short by about 1,200 sq ft. Fortunately, +/- 800 sq ft appeared on Craigslist the first day I realized that I was short. For the remainder, I tried networking with carpet layers who are willing to keep the pieces large until I could come by and help carry them out.
However, I found that carpet layers remove old carpet by cutting it into narrow strips that, when rolled up, are easy to carry out of the building, and that those I contacted did not want to bother with an alternative approach.  I ended up dumpster-diving behind a floor covering store (with permission) to find pieces big enough to finish the project.

We laid the carpet upside down in two layers, each in shingle fashion to shed water that
We ran out of carpet when the larger area in the distance
was covered with two layers but the area in the middle
distance had only one layer of carpet and the area in the
near distance had none; nevertheless, it was possible to
begin the backfilling while obtaining more carpet as
evidences by the track loader in the background
would be flowing on top of it and taking care to mismatch the junctions between pieces in the two layers so that all areas were sure to have at least two layers of protection between the topsoil and the sheet plastic.  We also unexpectedly found that it was best to lay the first layer right-side-up for a couple of reasons. First, and most important, rolled carpet always seems to come with the backing side out and, when unrolled, has the appearance side up.  If we were to have insisted that the first layer be upside down as originally planned, we would have had to unroll it and re-roll it to be able to position it correctly without disturbing the sand.  To say it another way, it would not have worked to have unrolled it then dragged it into position across the sand, as opposed to merely unrolling it across the area of sand that needed covering.  There was a second reason for laying the first layer right-side-up. After the first layer was in place and we were laying the second layer upside-down, it was easy to keep track of which areas had not been covered with the second layer. Having the "good side" of the first layer exposed meant that, at a glance, we could see which areas had not yet been covered with upside-down carpet.  The second layer was easier to lay in that it did not have to be unrolled precisely where it was to end up -- it could be unrolled close to its final destination and dragged to place across the first layer of carpet.


A Couple of Additional Nuggets
Hiat, the principal authority on the envelope, warned that the plastic sheeting would probably be punctured while laying it but not enough that its function would be compromised.  However, we saw no evidence of punctures.  6 mil plastic is pretty tough stuff and the layers of sand cushioned it from the underlying rough soil and gave it enough resiliency that we could walk on it with abandon.

The carpet must be of synthetic fibers, not wool, in order not to biodegrade in the soil.  Also, it is important to protect the carpet from UV rays while in storage which is as simple as covering it with tarps that are of sufficient quality to resist UV disintegration themselves. We had to discard a few yards of carpet that were not adequately protected by the tarps. Another benefit of keeping them covered is that they stay dry and are lighter when handling them for the umbrella.

          *          *          *          *          *          *          *          *          *          *

The topsoil backfill will be the subject of the next post, especially how we solved the dilemma of using the track loader on top of the envelope without crushing it.