Pouring the Concrete Walls
Here's where I had to stand aside and watch. Jamie Schulte and his crew of +/-8
Forms in place; ready for the pour. |
Once the concrete guys were gone, I dismantled the forms for the footings and turned my attention to the footings under the stick-built walls.
Pouring the wall from a pump truck |
Narrow Footing for the Stick-Built Walls
Unlike the wide footing under the concrete walls that was poured largely without forms, the narrow footing was poured in wood forms entirely. The choice of wood forms was based upon the low tolerances specified for the insulated concrete forms that will be used on top of the footing for the foundation walls. The specs for level call for no more than 1/4" variance. However, we were later to find out that our best efforts at forming up and pouring a level footing still yielded a variance of 7/8" over the span of 164 linear feet of footing.
For an 8" thick concrete wall, the code minimum for the footing is 8" thick and 16" wide. The forms were set for 8" thick and slightly more than 16" wide using salvaged 1 x 8s lubricated with diesel oil. For the +/-20' section over the conduits for the solar collector, the thickness was increased to 16". The design of the forms was taken from Chapter 7 in the book, "Carpentry & Building Construction; A Do-It-Yourself Guide" by William P Spence. It took several days to get the forms ready for the pour. My step-son and a friend, a journeyman carpenter, contributed 2 1/2 man-days towards building the forms. Surprisingly, it took me as much time to wire in the rebar as three of us took to build the forms.
Rebar Configuration
As with the wide footing, bolsters with plastic sheeting under them were used to support
In earlier times, a rhomboidal-shaped two-by-four was typically nestled into the top of the fresh footing concrete to create a "keyway" depression into which the base of the concrete wall locked. That practice seems to have been abandoned in more recent times in favor of "L"-shaped rebars projecting upward from the footing to be incorporated in the wall. In our case, the plans called for vertical rebar on 2' centers (which matched the situation in the wide footing for the concrete walls as described in the
The vertical "L-bars" could not be plunged into the fresh concrete randomly but had to be
The poured wall and the forms for the narrow footing ready to pour; notice the deadmen behind the wall. |
removed so they did not interfere with screeding off of the fore and aft form boards as Pat is doing in the photo below. As the concrete gained stiffness, the L-bars were straightened as much as possible with the intention of making them perfectly vertical by bending them later if necessary. Later, when the forms were set up, a few rebars had to be redirected but none had to be cut off and repositioned.
Pouring the narrow footing was definitely within the grasp of the DIYer. Five of us amateurs were able to off-load the concrete and get it screeded before it began to set -- but
Friend, Pat, and family volunteer, Archie, screed; off-loading concrete utilizing the extra 14' of chute |
The bottom photo is included to show the relationship of the narrow and wide footings. The insulation was cut away and shallow holes were made in the wide footing into which the horizontal rebar in the narrow footing fitted. The concrete in the narrow footing cold-jointed with that of the wide footing.
Fortunately, for the first time this year, rainfall has been, for over a month, less than normal providing the perfect weather for the concrete work. We were able to get the narrow footings poured while the dry weather persisted. My hope is that we can get the foundation walls up while it is still dry.
Parenthetically, the Building Director who inspected the forms before the pour, was very complimentary, saying something like "this is the way it is supposed to be done and rarely is".
Foundation French Drain
If I am not mistaken the code that Collinsville is using, requires a footing/foundation French drain -- as well it should. In
Junction between wide and narrow footings. Notice he loose end of the French drain and the fact that it is bedded in sand instead of rock. |
The one thing we did that was not a compromise was to trench for the drain next to the footing so as to keep it below floor level and slope it gradually to daylight. (Apparently, it is not uncommon for the drain to be laid on top of the footing against the wall.) But, that said, there were a couple of compromises. I used corrugated and perforated drain pipe with a sock on it from the local big box home center knowing full well that the sock will not filter out our wind-blown loess soil forever, that it will eventually allow the drain to clog with silt. Moreover, instead of bedding it in clean stone, I used sand, which will work as well and almost as long as stone before clogging with silt.
Since I plan to backfill in 5' layers and let nature do the compaction, as opposed to shallow lifts and mechanical compaction, the umbrella and final grade will be months away. Therefore, an atypical rationale for the drain was advocated by the concrete contractor. Even if it functions only temporarily, it will serve to keep the backfill drier and reduce the pressures against the wall as the backfill compacts over time. In this context, the compromises become acceptable.
This blog is really useful for me This is one of the most wonderful blog i love it ... !
ReplyDeleteconcrete plastic forms
This blog is a great reference. My husband and I really want to build our own green home, but I was pretty intimidated at first, especially with things like the foundation. But after doing some looking online and finding this blog and reading this article, I feel like, with a little help, we could actually do this.
ReplyDeleteKendra Tran @ LECO Concrete Forms
The intent of the blog is to ping sustainability a tad and to help other DIYers. Your feedback is welcome validation. Thanks.
ReplyDeleteI my view, some of the things you will need for success with your project are (1) unrelenting research, (2) decent handyperson skills, (3) proper tools, (4) an open-minded building inspector and, most important (5) a willingness to being task-oriented instead of time-oriented (it will take a lot longer than you think). Oh, I should add: a few volunteers when you really need more hands.
Good luck, Kendra.
"This blog post is very informative and well-organized. The section on pipe relining services is particularly useful. Keep up the great work!" Ironside Designer Homes is your premier choice for Building Designers in Brisbane.
ReplyDeleteThank you for this well-written post on building inspections. The way you cover building construction services is impressive and very informative. Total Building Inspections QLD is your premier choice for comprehensive service of Building Inspections Morayfield.
ReplyDelete