The first post detailed the conduits that carry the heat from the summer sun to the thermal mass under and around the house. The second post focused on size of the solar collector and the excavations necessary to build it into the slope in front of the house. This post deals mostly with the construction of the shell for the collector, connecting the conduits to the collector and closing up the excavation. (Click on any photo to enlarge it..)
Walls
Since the collector is buried in the ground, the walls have to brace several feet of backfill. It could have been constructed with poured concrete on a poured footing resting on virgin soil, similar to a foundation wall. In order to save money and to be able to design it as we went, I opted for dry-stacked concrete blocks resting on virgin soil and sand. The first course
Bond beam course partially filled; horizontal rebar in place |
The collector will need a fence to meet code. The decision between mounting it on the top of the walls or setting it back a ways so as not to shade the collector will be made eventually after observing the solar gain on the finished collector. The fence will also have to be designed to keep small non-climbing critters out. As far as deer are concerned, all we can do is pray that one doesn't jump in and land on the glass.
The tall north wall was reinforced horizontally with three courses of bond beam blocks filled with concrete and #4 re-bar -- one bond beam course near the bottom, another halfway up and the other near the top. The other three walls, since they were shorter, had only two bond beam courses. The cores of the corner blocks and the cores of about a half of the intervening blocks for all four walls were filled vertically with concrete, except, as explained below, the south wall had fewer unfilled cores.
Extending about a foot downward into the soil from the bottom of vertically-filled cores in all four walls were 3" Schedule 40 PVC pipes that were filled with concrete when the cores above them were filled. They also held the lower end of the vertical re-bars that rested on 2" PVC pipe caps dropped into the 3" pipes upside down. The purpose of the caps was to keep the rebar from coming in contact with the soil to eliminate the problem with the steel rusting, expanding and cracking the concrete. The purpose of the 3" PVC extensions, well anchored in undisturbed soil, was to resist the lateral pressure of the backfill against the bottom of the wall.
Fiber Bonded Cement Parge
Both sides of the walls were parged (stuccoed) with fiber-bonded cement as is typical with dry-stacked cinder blocks, except for the south wall where there was not
Closeup of a weep hole pre-made from a half block turned on edge; PVC pipe was concreted in and geo-textile fabric was added prior to dry stacking |
The integrity of the taller north wall was severely tested only a week or so after backfilling (without compaction) when, not one but two, concrete trucks parked on the backfill while pouring the footing for the north wall of the house. After the trucks left, the backfill was thoroughly compacted -- it had sunken by a foot and a half.
Weather Related Change
Two concrete trucks parked on the backfill for the collector with no ill-effects on the DIY walls of the collector. (Whew!) |
Managing the Water Problem During Construction and Beyond
It is a given that the collector, being in a pit, will collect water as well as sunlight. A good thing happened unexpectedly during the excavation that solved the water problem. The excavation for the collector was deep enough to uncover near its center one of the French drains but, unfortunately, beyond where it had been perforated (details on perforation). So I removed a 5' section of the exposed drain and substituted a new section that was copiously perforated and wrapped with the same geo-textile fabric used with the French drains originally. The replacement was sorely tested during numerous hard rains in May and continuing through early August because, as mentioned above, most of the runoff from the house footprint followed the conduits into the excavation for the collector. After a rain, the house footprint dried out within three or four days but the pit not for a week or so. However, without the serendipitous drain, water would have stood in the pit indefinitely because our wind-blown loess does not naturally drain as quickly as loamier soils.
The record rainfall in June was slightly more than three times that of normal. To eliminate some of the runoff that had been so readily finding the collector, I finally resorted to covering the footprint of the house
The house footprint, except for garage, was covered with tarps; the soil, conduits and gravel behind house were covered with plastic |
The ends of some of the corrugated pipes are visible while others are hidden by collapsed soil and gravel that was undermined by runoff following the conduit trenches. |
Between now and when the time is right to finish the collector, presumably in about a year, the extra dirt that the water has deposited on the floor will have to be removed, the floor sloped towards the French drain and a few inches of white gravel added with landscaping fabric underneath. Once the excavation for the conduits and the space around the collector have been backfilled, the slab floor for the house has been poured and the insulation/watershed umbrella has been installed, the only water inside the collector will be limited to whatever falls into the collector itself and should be easily handled by the French drain.
The white gravel for the floor of the collector will be ideal for reflecting short wave length solar radiation and converting it into long wave length that cannot pass back through the glazing (greenhouse effect). The collector will be designed to funnel the resulting heat into the conduits where it will flow passively about 78' to daylight (20' of smooth pipe between the collector and the house, 38 ' of corrugated pipe under the house and another +/- 20' of smooth pipe behind the house).
With regard to plant growth inside the collector, the assumption is that, once the collector is finished, the temperature inside will be too hot for plant growth. The use of landscaping fabric under the gravel may therefore be unnecessary, at least for the hottest part of the summer. But maybe we will have created the perfect greenhouse and plants will be a big problem despite the fabric, in which case, more drastic and unwelcomed measures will be necessary -- only time will tell.
Parging the south wall with fiber bonded cement. Notice the anchor bolts for the 2 x 10 pressure treated boards that will cap the top of the wall. |
Insulation
In conjunction with installing the PVC pipes that bridge between the corrugated pipes and the collector, four sides of the excavation were insulated -- the floor, the north wall of the collector and the east and west walls. One layer of two-inch thick extruded polyethylene insulation board was laid on the floor of the excavation over a thin layer of sand. I considered using expanded polyethylene (Styrofoam) for a couple of reasons but opted for extruded with its 250 psi compressive strength since there will be 5 - 6' of backfill on top with vehicular traffic passing over during construction. The sides of the excavation were also insulated as was the outside of the north wall of the collector but, since these areas did not have to carry heavy loads, cheaper 150 psi was used.. Actually, the insulation for the north wall of the collector was mostly a freebie from the local farm and home store. It was Styrofoam in big chunks that were easily carved up with table and handsaws.
I decided to use extruded polyethylene for insulation with some trepidation after having run onto a YouTube posting showing water being rung from extruded poly which contradicts the claim of extruded polyethylene as to its low water absorption. (Water logging reduces R-value to near zero.) Expanded poly is used universally in wet environments from insulated concrete forms to boat docks, so maybe it makes sense to use it subgrade and devise ways of protecting it from loading. More on this subject in a subsequent post on the AGS insulation/watershed umbrella.
The primary reason for insulating the excavation at all is to prevent heat loss from the conduits to the soil in front of the house before it can reach the thermal mass under the
Backfilling with rock around the piers to help support the footings under the front wall of the house. |
Backfilling
Backfilling of the excavation was done in stages as soon as the collector walls were built, the rigid conduits were connected to the corrugated conduits and bedded in in sand, the insulation
Completing the backfill of the excavation over the AGS conduits that were bedded in sand ahead of time. |
First, clean rock was dropped in to provide a more compacted base for the footings, foundation wall and slab floor. The rest of the excavation was filled with uncompacted dirt which should be sufficiently settled by the time the insulation/watershed umbrella is installed.
Air Flow
Presumably, we will be ready by next summer to finish the collector which will include building the framework to support the glass. The south side of the framework, 18" in from the south wall, will comprise mostly air vents because the cross-sectional area of the vents will need to be considerably more than that of the cross-sectional area of the nine AGS conduits added together in order to be absolutely sure air flow through the conduits is not impeded by a lack of intake air. And the vents will require something like hardware cloth to keep critters out of the collector and conduits.
No comments:
Post a Comment
As a do-it-selfer-in-training, I welcome your comments.