Reality Check
Progress on the entire house-building project has been and will continue to be snail-paced mostly because of the limited amount of work a DIYer alone can accomplish. The agreement I had with the Building Director when applying for a permit is that, since I was responsible for the design of the house, the architectural drawings did not need to be as detailed as is typical. The upside of this arrangement is lower architect fees but the downside is that I have more stuff to keep track of on the fly. Not committing mind space to the garage floor at the time the site was excavated is a perfect example of how difficult it is for one person to prioritize and coordinate the myriad facets of construction. Some things have to be back-burnered until they are more pressing and some simply drop through the cracks.
Finally, the time came when the garage floor had to be dealt with and, by delaying, I created extra labor to get it right.
The original excavation would have been pretty accurate if it were not necessary to install the insulation/watershed umbrella under the floor as that part extending eastward from the house proper. But the excavation needed to be lowered at least by the thickness of the foam insulation board for the umbrella. So I tried to catch the soil at just the right time after a rain that it worked easily with hand tools -- which leads into an interesting discussion about our unique bluff soil.
Factoid About Our Unique Soil
In-letting for 4" of foam insulation |
Smooth sand base for the insulation |
Insulating the Garage Floor as Part of the Umbrella
Middle section of insulation in place |
Final section of insulation in place |
Raising the Height of the East Wall of the Garage
In retrospect, I should have designed a higher concrete east wall for the garage in order to
Rebar and door buck in place for adding four feet to the height of the east wall; notice also the 2 x 10 forms bridging the garage door openings |
Pouring the Garage Floor
The floor was designed to be 1 1/2" lower than the house floor at the back of the garage and 3" below at the front. I snapped chalk
The new east wall uncovered (in the background); the slab pour underway |
When Jamie and crew arrived, they removed the wall forms and, while waiting for the ready-mix truck, plate-compacted the sand that I had soaked the night before and installed 6 mil plastic sheeting. The day was warm so the pour cured rather fast and could be finished by early afternoon.
Handling the Cold Joint Between the Wall Addition and the Foundation
My design and management of the east wall of the garage was driven too much by cost.
There are three deadmen in the middle of the north wall; the fourth and fifth are affected by turning the corners and involving the east and west walls |
The disadvantage of retrofitting the east wall is that a cold joint is formed between the concrete of the insulated concrete form foundation and the new wall. My concern was that the joint would leak water into the garage. So how to fix it?
One possibility was to gunk up the joint on the exterior with tar-like materials and hope that
they would not lose their effectiveness with age, assuming they adequately sealed the joint in the first place, given the contamination of the surfaces by deposited dirt. The other possibility was to install a proper French drain opposite the joint to siphon water away before it could infiltrate the joint. I oped for the latter.
Typical French Drain Installation
There was already a footing-level French drain so it was a matter of uncovering it and inserting a wye for the new drain (first photo). I then lined the ditch with left-over geo-textile fabric and fastened it to the wall temporarily (second photo). As is typical with French drains, I covered the bottom of the fabric with a couple of inches of 3/4" clean rock before laying in the pipe and connecting it to the wye (third photo). More rock was added to cover the pipe. The edges of the fabric were overlapped to cover the rock and secured with hog rings (third photo).
The drain was left exposed instead of backfilling immediately because the outside of the garage wall will have to be insulated before the soil is added. It will be insulated in the manner that was described in an earlier post . As soon as the wall is insulated and covered with stucco, I will backfill nearly to the top of the wall at the back and sloped towards the bottom of the wall at the front.
Consequently, I used home center perforated pipe with a sock, no fabric lining for the ditch and sand instead of rock for the drainage plane. If there were to be no umbrella, I would have bought perforated pipe and covered it myself with the geo-textile material shown here that has been scientifically designed for fine silt soil like we have. The store-bought fabric that I did use instead of the special fabric can be expected, in the absence of an umbrella, to admit enough silt to clog the pipe and render the drain useless eventually. The same would be true for lining the ditch with local store-bought material -- it would not filter the silt sufficiently to keep the gravel bed clean and unclogged indefinitely.