Thursday, October 22, 2015

Construction - Concrete Work - Plumbing and Electrical Rough-in Under Slab Floor

This is the fifth post on the concrete phase of construction and I apologize for its length but countless surprises challenged my DIY-ness and I would be remiss if I did not pass them along for whatever they may be worth.

With regard to the concrete per se, all that remained was to "sling" in the gravel sub-base and pour the slab floor. However, both tasks had to wait until the plumbing that resides below the concrete had been roughed in. The rough-in comprised not only the typical waste/sewer system but, in our case, the complete water supply system as well. And a considerable amount of electric could be roughed in before the pour. (Reminder:  Click on any photo to enlarge it.)

Waste Plumbing Rough-in
In conjunction with pouring the footing under the front wall of the house, a short section of 4" PVC pipe was inserted below the footing forms with a foot or so extending
Waste plumbing rough-in; notice the that it connects with
and exits through the section previously installed
under the footing
beyond the forms on both the outside and inside to facilitate running the sewer line. The same was done with 2" PVC for the water line. The 
outbound sewer line connected directly to the 4" but the water line merely used the 2" to hold space until a 1" water supply pipe between the house and the water main at the street could be installed.

Installation of the waste lines was a matter of trenching into the excavation just deep enough to have the correct fall for proper drainage.  The downstream pipes were well below the grade and the upstream most pipes were almost at grade. The only thing that complicated the installation was trenching through soil that was more like stone than dirt, thanks to a layer of what old-timers called "hardpan" that presented even more of a challenge by not having seen a rain for almost a month.  The good news was that it will make a great base on which to rest a house.


The installation of the waste system was less complicated than our iteration of the water supply system but it does give meaning to the old saying, "Trifles make perfection but perfection is no trifle".  It requires a lot of know-how and attention to detail.  Fortunately, between two friends and I, we had enough composite knowledge to put together a system that passed inspection the first time.

PEX Rough-in for Water System
Our water supply system comprises PEX (cross-linked polyethylene) tubing as much as possible.  PEX was used extensively in Europe for potable water several decades before finding its way to the US in the mid-80s (it was used in the US before then for radiant floor heating but not for potable water).  Even though it is not used yet by many tradesmen, it meets code in most places and has many advantages over copper and plastic pipes. (For a thorough discussion, go to design guide for PEX plumbing.) Its major advantages for our project are simplicity, significantly lower cost and DIY-friendliness.

The myriad design options for PEX are well covered in the above link.  Suffice it to say that, for our project, only two major decisions had to be made. First, do we run separate "home run" lines to each appliance and fixture or do we run trunk lines to areas like the kitchen and bathrooms then branch off to the individual appliance or fixture?  Second, do we run the lines beneath the concrete floor or run them more conventionally through the framework of the house?  We opted for home runs and below the slab.  Actually, the two are linked in that only continuous tubes of PEX, free of any fittings, can be buried.  By marrying home running with burying, the rough in for the supply system was essentially complete before pouring the floor, much less waiting for the framing to be done, and at a fraction of the cost of doing it later.

Underground Installation
If PEX is buried, it needs to be protected from injury while the rock sub-base is slung in place and the slab itself is poured.  Moreover, it must be protected from chafing where it enters and exits the concrete.  These issues are usually handled by trenching into the dirt, covering the PEX with dirt, sand or pea gravel and providing short sections of conduit for the tubing where it leaves the dirt, sand or gravel and passes through the concrete. My lack of experience made me cautious to the extent that I decided to use conduits for the entire length of each home run -- from a couple of feet above the floor level at the upstream end near the water main and water heater to a couple of feet above the floor at the downstream end in wet walls near the appliances and fixtures.  The loosely-fitting conduits gave me the security of being able to retrieve the PEX if, for some reason, it wasn't working out as intended.  Also the conduits obviated the need for trenching in that they were robust enough to lie on top of the grade and withstand the slinging of the rock sub-base and the weight of the concrete.  Most were buried in the gravel, a few showed after the gravel was slung but barely.  Using so  much PVC did increase cost but not significantly.

When the decision was made to enclose PEX in conduits, I experimented in the aisle of my favorite home center using a length of 1/2" PEX, various diameters of Schedule 40 PVC pipe and 45 degree fittings.  As a result, I decided that 1 1/2" PVC pipe would be the smallest possible diameter for ease of insertion of the PEX for the 20 - 30' distances required and for the bends necessary to enter and exit the concrete. And, supposedly, the tubing could just as easily be removed from the conduits in the future if necessary.

Wrong!  As a trial, I glued together the PVC for one of the longest runs, tried to push the 1/2" PEX tubing through it and found that it hung up and couldn't be budged past the rough edge of the second 45 it encountered.  I tried to run an electrical fish tape in from the other end so as to pull the PEX and it too hung up immediately. Consequently, it was necessary for all 20 home runs to push the PEX past each fitting before gluing the fitting.  Fortunately, the PEX was not effected by the PVC primer or the adhesive so there was no danger of gluing the PEX to the conduits.  If a PEX line needs to be retrieved and replaced in the future, the thought comes to mind that a plumber's snake would negotiate the rough fittings and could be used as a fish line for pulling the tubing through the conduit or, better yet, the old tubing could be used to pull the new through the conduit.  

As it turns out, 1 1/2" PVC was the right choice.  PEX is a stiff material with a strong memory that wants to stay coiled up. Over distances of 35", 1 1/2" barely allowed the PEX to be pushed through.  Even the 10' sections of pipe between fittings offered sufficient resistance that I think a smaller diameter conduit could not handle easily. In one instance, I tried pushing two PEX tubes through in tandem and quickly decided that the effort was not worth the savings on conduit.  

Controlling the Entry and Exit Points for the Conduits
The biggest challenge to running the PEX system was to have it enter and exit the concrete at a perpendicular angle and be properly located inside the wet walls adjacent to fixtures and appliances.  To have any part of the conduit exit outside the wall would be unacceptable. 

The supply system rough-in completed:  Bathrooms to the
left, kitchen island sink and laundry to the right; future
manifold area in the background; second kitchen sink out
view to the right
Consequently, to control the ends of the conduits,  I shop-made salvaged 2 x 4 supports.  One set had 2 1/4" holes for the conduits and an identical set had 7/8" holes for the PEX.  Five foot sections of 4" PVC pipe were used as posts to hold the 2 x 4s in place.  Since the buried portion of the posts would remain in the concrete, I chose plastic posts over metal to eliminate the possibility of the metal rusting, expanding and cracking the concrete.  Wood posts were out of the question for termite reasons. Eventually, the PVC posts will be sheared off flush with the floor and filled with concrete. In many cases, the stub-outs of the waste plumbing rough-in could be used in lieu of or in tandem with temporary posts.  I chose 4" posts only because 2-hole metal straps were available for fastening the 2 x 4s to them and the pipes were left-overs.
Manifolds with cut-offs for each home run

Looking ahead, the beginning ends of the PEX lines will be joined to copper manifolds with individual cut-offs for each line, much like a circuit breaker for each electrical circuit in a service panel. Eventually, copper pipes will run from the tankless water heater to the hot water manifold(s) while PEX will suffice between the water main shut-off and the manifold(s) for the cold water supply. 

The PEX at the fixture/appliance end of the lines will be supported by brackets attached to the framing and stubbed out of the wall for uninterrupted connection to faucets and appliances.  Or perhaps, I will use a copper stub out. In either case, only three or four fittings per line will be necessary -- two at the manifold end and one or two at the fixture/appliance end. And, of course, there will be no need for cut-offs adjacent to the fixtures and appliances because cut-offs are built into the manifolds.
Bracket-supported PEX for direct
connection to faucets
PEX with copper connection for faucet

Materials Cost
The rough-in cost for the waste and supply materials was only $300. However, when the cost of PVC conduits was added, the total cost was $841. I consider the $541 for the conduits to be cheap insurance against damaged PEX lines and not having the option of retrievability in the future.

Other Advantages to Home-running
Compared to trunk and branch systems, the home run system requires more PEX tubing but far fewer fittings. Since the cost of tubing is much less than the cost fittings, home running is cheaper. And, a traditional copper pipe system would cost even thousands more due to the higher cost of copper and, for underground installation, someone who is capable of soldering with silver solder. Another advantage to an underground home run system is quicker hot water. Compared to a home run system run through the framing, the quickness derives from the shorter distance between the water heater and the fixtures.  A trunk in a trunk and branch system requires a larger pipe (usually 3/4") than the branches (1/2").  This means that, compared to a home run system with all 1/2" pipes, there is more cold water in the system to be pushed out by the hot water.

Home Run Electrical Conduits
Electrical conduits from future breaker panel area to areas
that would be hard to reach by running wire through the
 framework of the house, e.g., the island sink in the kitchen
to the right in the picture or the front wall of the house to the
left
After the water supply rough-in was complete, one last job remained before pouring the floor -- running electrical conduit.  Being able to make long runs sub-concrete simplified getting service to areas remote from the future breaker box, especially where the open floor plan (living room, dining room and kitchen) and cathedral ceilings would significantly complicate running wires through partitions and ceilings. I ran 3/4" conduit for two reasons -- being unfamiliar with pulling wires through conduits, I figured bigger was better and 3/4" gave the option of  pulling two or three sets of wires when only one or two might really be necessary.  If one or two sets remain unused in the future, there would be no downside
Stub-in for future floor receptacle in the form of a space-
holding tin can; the black pipe in the background, the water
 supply line coming in from the street, is wrapped with pipe
 insulation to keep the water cool as it passes through the
thermal mass under the floor when it is warmed by the AGS
 system eventually
since I fell heir to several spools of wire when helping to ready our former church for a remodel. 


The need for a floor receptacle was met by using a tin can to hold space during the pour.  A hole saw in the drill press, provided access for the conduit  through the bottom.  The rotating laser located the top of the can 2" above the pour, a stone supported it and a length of rebar piercing the bottom the can and driven into the soil at an angle stabilized it.

*     *     *     *     *     *     *     *
October 2019 Update
The final rough-in for the plumbing was completed four years later.  Here is the link to the later post on the plumbing rough-in.  Of special interest is its description of the manifold, tankless water heater and the automatic overflow prevention, all part of the PEX home-run system.

Friday, October 16, 2015

Construction - Concrete Work - Insulated Concrete Forms

This is the fourth post on the concrete phase of construction.  It details the unconventional foundation under the stick-built walls.  The first post on concrete work covered the excavations for the footings.  The second dealt with pouring the wide footings and concrete walls.  A third detailed the narrow footings under the stick-built walls.  Here we dwell on the rather unique and unconventional foundation wall, poured in insulated concrete forms to support the stick-built walls.  (Click on any photo to enlarge it for closer inspection).

Shallow Frost Protected Foundation
Our foundation is based on a recent "green" innovation that has actually found its way into the International Building Codes.  It is called a "shallow frost-protected foundation" (see the earlier post on shallow frost-protected foundation).  Instead of the top of the footing for the foundation being below the frost line, it is protected by insulation so that it can be much closer to the surface.  Our plans call for a 20" foundation wall, i.e., the distance from the top of the footing to the top of the foundation is 20".  For termite reasons, the code calls for an 8" separation between the soil and the wood elements of the structure.  If this dimension is subtracted from the height of the foundation wall, the top of the footing is only 12" from the grade instead of the +/-30" needed to get below the frost line.  This represents a 46% dividend in terms of embodied energy in the concrete as well as a few dollars saved on the volume of concrete.  However, the forms do not come cheap (a little over $1,200 for the 164 linear feet  20" high).  It would have been almost twice as much if the forms were used to pour a conventional foundation that reached below the frost line.  However, it must be said that, for a first-timer, the installation was unexpectedly time-consuming and frustrating, due largely to the unevenness of our footing.


Amvic Insulated Concrete Forms
The brand of  insulated concrete forms (ICFs) that I selected was the Amvic System because it were available from a local supplier and was manufactured in Missouri, both of which help to minimize embodied energy which is an important sustainability issue.

Installing the Insulated Concrete Forms on the Narrow Footing
Let me say upfront that our installation had little in common with that detailed in the "ICF Technical & Installation Manual" for the Amvic System.  The need for improvisation was entirely my fault by not getting the footing perfectly level throughout.  In retrospect, it would have taken rented metal forms installed with huge precision to have met Amvic's spec of 1/4" variance for levelness.  But salvaged  2 x 8s, despite being a lot more work to install, not always straight-edged and impossible to install precisely, were free and produced a leveler footing than would have been possible by pouring directly against the soil in a trench.

The Amvic ICFs are available for wall thicknesses of 4" to 10" of concrete with 2 1/2" of expanded polystyrene ("styrofoam") on either side,  The styrofoam serves first as the outside and inside forms into which the concrete is poured.  The "Dixie Cup" walls are strong enough to handle the concrete by virtue of internal webs that hold the two sides together.  Secondly, the forms stay in place after the pour as R-22+ insulation.  Our ICFs were for 8" walls such that the overall thickness, styrofoam included, was 13".  The 20" height for the wall was achieved by using one course of blocks 16" high then adding a 4" so-called "height adjuster" course to the top.  The smooth top of the height adjuster also facilitated screeding the top of the wall when the concrete was poured.

Our house plans give the dimensions of the foundation wall in terms of the exterior plane of an 8" wall and the batter boards had been set to these exterior dimensions. The ICFs then had to be installed on the newly-poured footing so that the concrete poured into them matched the batter boards.  To this end, mason lines were strung one last time between batter boards so that the equivalent of corner posts could be established and marked with concrete screws on top of the footing.  A chalk line was then tensioned between screws and snapped to give the position of the inside edge of the exterior styrofoam, which is to say, the outside edge of the concrete when it is poured inside the styrofoam.
Chalk line wrapped around a corner screw and
 ready to snap for a layout line.

We used a technique for aligning the forms that the installation manual recommended, viz., 2 1/2" steel drywall tracks for precise positioning of the ICFs along the chalk line. The tracks were fastened with Tapcon concrete screws on the chalk line so that the outside styrofoam of the ICFs, when seated in the track, would give a perfectly straight wall.  But "straight" is not the complete answer -- the wall has to be level if the foundation is to be level.  Despite working so hard using wood forms to control the levelness of the footing, there was a variance of about an inch over 164 linear feet. Therefore, the variance had to be finessed as the ICFs were installed through a combination of shimming (raising) under the low spots and shaving the bottom of the ICFs (lowering) over the high spots (all of which was much more time-consuming than expected).

Leveling the ICFs Longitudinally 
Thank goodness for a rotating laser when working alone.  I used it first to survey the top of the entire footing at +/- ten foot intervals to see how much variance there was and where the highs and lows were located.  Based on that data, I picked a default height that was weighted towards shimming (raising up) rather than trimming the bottoms of the ICFs.  As a consequence, the highest shim was +/-3/4" and the most that the bottoms of the ICFs had to be trimmed was +/-1/4" and the latter occurred only over 10-15' linear feet distributed over three areas.  

Installing the Metal Track
The first task was to drill holes in the tracks so they could be screwed to the footing with Tapcon screws. The easiest way to do so was ahead of time with a drill press.The installation was started where the track could be fastened without shims at the default height.  As the installation proceeded around the footing, the following steps emerged as the best approach ("proximal end" means the end next to the last section installed and "distal end" means the end farthest from the last section):

-  Lay the track on the chalk line
-  Fasten the proximal end first guessing (based upon laser readings) as to the amount of
Friend, Glen, leveling
the track with laser
 guidance.  Click on
 the photo to see the
 shims under the track
 shimming necessary and placing the shim(s) adjacent to the screw rather than drilling through them 
-  Since part of the shims will remained in the concrete avoid using wood shims to avoid attracting termites; use plastic shims, either store-bought or made from styrofoam trimmings
-  Fasten the distal end of the track on the chalk line without regard to shimming
-  Check the proximal end with the laser; loosen the screw, adjust the shimming as necessary and retighten the screw
 -  Check the distal end with the laser, loosen the screw and shim as necessary
 -  Through each of the intervening pre-drilled holes in the track, drill holes in the
 concrete
 -  Add the screws; shim beside each screw, guessing as to the thickness; tighten the screw and check with the laser; if necessary, loosen the screw and finesse the shim height
-  Helpful hint:  Before shimming, press down on the track above a screw hole with the laser measuring rod to get a read on the shim thickness required then add the screw and the shim; doing so eliminates some of the trial and error and tends to speed up the process.

Leveling the ICFs Transversely 
So the above efforts leveled the outside styrofoam but the inside styrofoam was still a mess. The ICF blocks are sufficiently rigid that the inside foam goes along for the ride longitudinally but they still need leveling transversely. And, of course, transverse leveling also plumbs the wall.  We tried two methods but the one that worked best was to wait on the inside shims until the forms were leveled longitudinally.  Then, in conjunction with plumbing and leveling the forms, shims were added as necessary.

Attaching the Forms to the Footing
The disadvantage of opting for more shimming and less shaving to achieve levelness was that there was a space between the metal track holding the outside styrofoam and even more space under the inside styrofoam that did not have a track taking up space.  The manufacturer recommends using a proprietary foam and sprayer to fill the space and "glue" the forms to the concrete. The customer service person at the local supplier suggested, since our project was a one-time and small project, not to invest in the sprayer but to use a spray adhesive instead. It wasn't until we were ready to use it did we realize that the styrofoam must be in intimate contact with the concrete for the adhesive to work.   So how do we DIY a way to fasten the forms to the footing and obliterate the gap under them so that the concrete does not raise the forms or leak out under them? 

(This then is the point of departure from the technical manual).  First we ripped enough 1 x
The 1 x 2s were fastened to the concrete.  To the right,
one layer sealed off the bottom but, to the left, two
layers were necessary due to unevenness of the footing.
2s from salvaged lumber to circumvent the entire ICF setup on both sides, butted them against the forms and fastened them to the footing with Tapcon screws.  This stabilized the bottom of the forms from the lateral pressures of the concrete during the pour and largely sealed off the space under the forms (there was the equivalent of 70 linear feet, randomly situated, that needed a second layer of 1 x 2s and 30 linear feet that sat directly on the concrete). However, the 1 x 2s did not keep the forms from lifting as would be expected from adhesive foam recommended by the technical manual.


While actually exceeding the manufacturer's specs for spacing of vertical bracing, we used 2 x 4s resting on top of the 1 x 2s and stopping just short of the top of the wall. The verticals were drywall-screwed into the plastic webs that tie the two sides of the forms together -- the same ones that serve as "studs" for fastening the exterior and interior finishes later. Then we used drywall screws and Tapcon screws to anchor to the footing by toenailing the verticals to the 1 x 2s or, where they did not exist, directly to the footing.  As recommended by the manufacturer, the basic 16" x 48" ICF straight blocks in the first course were tie-wired together then extra verticals were added where adjacent blocks were still a little unstable or unlevel.

Strongbacks and Lateral Bracing
In additional to vertical bracing, there needs to be lateral bracing.  We chose to do it on the interior of the forms so as to have it out of the way of pouring the concrete. The verticals on the interior of the forms provided solid fastening for the braces.The verticals on the exterior of the forms, though anchoring the forms and supporting the strongbacks, did not receive
View showing the verticals, strongbacks and braces
any braces since 
bracing was necessary only on one side of the forms.  The exception was a "T-wall" that intersected the exterior wall.  Here exterior bracing was necessary because, without the bracing, the weight of the concrete in the leg of the "T" might cause a blow-out.

Strongbacks would have been overkill if the wall had not been topped off with the 4" height adjusters that gripped the course below rather tenuously and looked suspiciously vulnerable to displacement during the pour.  So, as an insecure amateur, I needed the strongbacks as insurance..

Garage Door Cutouts
The garage floor will overlap the foundation below the two garage doors.  Therefore, the
Cutouts for the garage doors 
ICF forms needed to be 9" shorter under the doors, which is to say the forms had to be shortened by that amount.  Despite leaving the 4" extensions off, the blocks below needed to be shorten 5" but doing so presented a dilemma in that the all-important tops of the webs in the forms would have to be cut which would severely weaken the walls of the forms.  I elected to
Garage door area - final configuration
cut 
away only the unsupported foam between the webs, thinking that I could finesse the cutouts after the concrete cured.  And the vertical rebars that were fine for the rest of the foundation were too long at the cutouts.  It was a simple matter to shorten them after they were stabilized by the concrete.
Rebar extending into existing wall

In order to transition the concrete from the higher foundation walls to the lower cutouts, 2 x 8 pressure treated blocks-outs were cut at 8" to fit inside the ICFs. They were anchored in place with 6" TimberLok construction screws that pierced the vertical braces (existing or added specifically to support the block-outs) and the foam before screwing into the treated members.  The block-outs were held at least 1 1/2"  back from the eventual rough door opening so as to accomodate two-by framing for the door opening and still maintain a 9' opening.

Tying Walls Together
The joint between the existing concrete walls and the new foundation wall was a "cold joint", meaning they merely abut each other but are not physically joined. In order to keep the relationship between them from shifting, the rebar from the foundation wall was extended into the existing wall by drilling holes a couple of inches deep for the rebar in the foundation wall. 

Pouring the ICFs

It took 5.5 yards of concrete, a conveyor truck and five volunteer workers to pour the forms
Forms poured and anchor bolts in place
with relatively little effort -- definitely a DIY-capable endeavor.  And I am happy to report that the installation of the ICFs was sufficiently robust to eliminate any potential blow-outs.


Quality Control Issue with the ICFs
The ICFs are understandably fragile. Some components were damaged in transit and were unusable.  The height adjusters that were 1/8 to 1/4" shorter than the straight blocks and had to be split in half
Poured foundation after bracing removal
and, even then, somewhat forced to place. The design of the corner blocks have been upgraded for better retention of cladding materials but the height adjusters have not been ungraded.  Consequently, both the adjusters and the corner blocks had to be modified with a knife to maintain levelness. Cutting and fitting two halves of the adjuster separately left space that I filled with minimal expanding spray foam, which actually may have been an advantage in that the adjusters were glued together and perhaps more stable.


Would I use ICFs again?  In a heartbeat, but only after more research before buying.